Copy Element of Cost Value to Child Resources
Use this procedure to copy the element of cost value attached to a parent resource to its child resources.
To copy element of cost value to child resources, complete the following steps:
- Display the Resource view of the resource file that you want to update.
-
In the Resource view, click a parent resource and take one of the following actions:
- In the Codes group on the Resource Edit tab, click Copy Element of Cost.
- Right-click the Resources grid and select Copy Element of Cost.
Note: The Copy Element of Cost option is enabled only for resources with child resources. - Click Yes when the confirmation message displays.
- Click to save your changes.